Location

Blandford Forum, Dorset

Lead Time

4 weeks

Products

  • Tyre Racking
  • Warehouse Safety Steps
  • Load Notices

Time on site

One week

Additional Details

Our client wanted to create more space for an MOT bay as well as increase the number of tyres they stored on site.

We removed and disposed of a section of the existing mezzanine floor to create more floor space for the MOT bay. New handrailing was installed to the mezzanine to the exposed edges of the mezzanine floor.

Tyre Racking with four storage levels was installed into the remaining mezzanine.

Walk through tyre racking bays were designed into the scheme minimise wasted space.

Spreader plates were installed under the racking frames to spread the load of the new racks when loaded with tyres.

Finally, we supplied warehouse safety steps to access the upper levels of the racking.

Other Case Studies

Free on site advice and consultation to understand the specific requirements of
each client

Call Us Now